Integrated system deliverables

LayerReleased project definition
Player / ComputeSource files, player, OS image, CMS, codec and update method
Display controlOLED controller, LED processor or embedded display electronics
Signal and CablingInput, conversion, protection, cable schedule and connection map
InstallationStructure, glass, mounting, thermal path and service access
OperationsMonitoring, recovery, spares, acceptance record and handover

A demonstration proves that one configuration can display one piece of content under the conditions of that demonstration. Handover asks a larger question: can the installed system meet its requirements, recover from expected faults and be operated by the receiving team?

In an August 2026 discussion, an owner describes running out of usable spares after the supplying company closed. Include service records, compatible replacement parts and a recovery procedure in the acceptance package.

Complete display system layers connecting content, playback, control, display hardware, power, structure and service
The system becomes reproducible when every layer and interface has a defined owner and acceptance method. Functional diagram; not to scale. Open full-size diagram. Scroll horizontally to inspect all blocks.

Start with a traceable requirement

Give each acceptance item an identifier, an owner, a configuration baseline and an agreed pass condition. A useful baseline identifies hardware revisions, firmware, player image, content package, cabling and processor settings. Store the report beside the configuration it tested.

AVIXA’s performance-verification framework supports relating project requirements to verification and reporting. The FAT/SAT/operations structure below is our proposed project workflow; it is not a claim that AVIXA prescribes these exact stages or limits.

Use each acceptance stage for a different question

StageQuestionRecord the remaining gap
FAT: before shipmentDoes the released hardware/software configuration meet the agreed factory test plan?Simulated interfaces, temporary cabling and untested site conditions
SAT: installed systemDoes it work with the actual mounting, power, network, cable routes and environment?Open site defects, deviations and responsibility for closure
Operational acceptanceCan the receiving team operate, update, diagnose and restore it?Training, access, backups or support arrangements still missing

A practical test record

TestAction and observationPass condition to agree
Cold startFollow the approved shutdown/start procedure; time arrival of the correct contentCorrect application, input, map and content within the specified time
Network lossIsolate the agreed network link; observe local playback and monitoringAgreed fallback and truthful connection alarm
Signal lossInterrupt the approved test link; restore it and observe recoveryDefined display state; no unintended persistent input or map change
Content updatePublish a versioned test package; check every intended displayCorrect revision and schedule; rollback works if included in scope
Configuration restoreRestore onto an approved spare/test unit and verify the resultMatching mode, map, control behaviour and accepted image
Service replacementExchange the agreed field unit using its documented procedureMechanical fit, restored operation and acceptable visual matching

For each row, record preconditions, operator, timestamp, observed result, evidence location and deviations. An unexecuted test is “not tested,” not “pass.” Electrical, thermal, structural and environmental qualification require their own defined procedures and competent personnel; a playback checklist cannot replace them.

Demonstrate what redundancy actually covers

Trace the source, processor, transmission path, power distribution and receiving hardware. Identify shared components. Then test only the failover scenarios included in the design and approved test plan. Two inputs on a controller do not establish independent sources; two supplies on one feed do not protect against that feed failing.

Make one person recover it from the handover pack

Ask a qualified team member who did not configure the system to locate the correct backup, identify the spare and follow the recovery instructions. Record missing steps. Include drawings, cable/port labels, asset IDs, software versions, calibration records, approved settings, licences, access ownership and escalation details.

Measure service time from the beginning of access and isolation through configuration and visual verification. Timing only the module exchange understates the operational interruption.

Close changes as well as defects

If firmware, cabling, hardware or a processor preset changes after FAT, record the reason and assess affected checks. Repeat those checks on the new baseline. Preserve accepted deviations and remaining actions with owners and dates. The final deliverable is a recoverable, documented configuration with evidence against the agreed requirements.

Technical sources

About this guide: Use these project checks with acceptance limits agreed for the supplied configuration. VITREVIA supplies and integrates display systems directly from Shenzhen, China.

Download the editable test record (.txt)

Project checklist

Related product and project pages

Engineering foundations